Weekly Project Meeting Minutes Template | Status, Blockers, Action Points
Weekly meetings only work if each set of notes connects to the last: did last week's tasks get done, and is anyone handling what's stuck? That's why this template puts "Last week's action points" first.
What's in this template
- Meeting detailsProject name, week number, date, attendees, note-taker.
- Last week's action pointsCopy each action point from last week's notes and mark it done, in progress or slipped. For slipped items, add the reason and the new date.
- Progress updatesOne or two lines per workstream or owner: what got done and where it stands.
- Blockers and risksWhat's stuck, who or what you're waiting on, and what it could delay. Name who will follow up on each one.
- Decisions neededQuestions to settle in the meeting and the option chosen. If it needs to go up the chain, say to whom.
- This week's action pointsOne per line: task, owner, due date. This becomes next week's tracking list.
Filled-in example
Member Portal Redesign, Week 6
6 Oct 2026, 10:00–10:30 · Present: Jordan Pike (PM), Mei Lin Torres (design), Sam Okafor (back end), Hannah Brooks (front end)
Last week's action points
Finalise login page design | Mei Lin | Done
Member data migration script | Sam | In progress, expected 9 Oct
Front-end form validation | Hannah | Slipped to 13 Oct, waiting on API fields
Progress updates
Design: login and sign-up pages delivered; password reset page due this week.
Back end: migration script ran once in staging; 312 records have format errors.
Blockers and risks
The SMS verification supplier contract is still with legal. If it isn't signed by 15 Oct, launch may slip a week. Jordan will chase.
Decisions needed
312 bad records: flag them and skip migration for now; tidy them up by hand after launch.
This week's action points
Password reset page design | Mei Lin | 9 Oct
Send API field spec to front end | Sam | 8 Oct
Check contract status with legal, report back Friday | Jordan | 10 Oct
Tips for writing it
- Open last week's notes at the start of every meeting and go through them line by line. The most common failure of weekly minutes is action points no one looks at again.
- Write progress as concrete output ("delivered three page designs"), not "ongoing."
- For each blocker, say who you're waiting on and for what, or you'll see the same line next week.
- If something wasn't decided, write down who owes an answer and by when.
Let Osmi write it
Upload your weekly meeting and Osmi writes a summary of key points and action points, with the full transcript attached. You can also tell it what to focus on this time.
FAQ
Do I start a new document every week?
Yes, one per week, but keep the same format. Copy last week's "This week's action points" into the new "Last week's action points" so the two connect.
Should daily standups have minutes too?
A 15-minute standup usually only needs blockers and requests for help. The "Blockers and risks" section of this template is enough.
Do I need to report progress as a percentage?
Not necessarily. Percentages are often guesses. Listing what's done and what's left is easier to judge.